Install the GB200-NVL4 board
Use this information to install the GB200-NVL4 board.
About this task
Screwdriver for PH 2, T10, and T15 screws
GB200 NVL4 NVLink interposer board installation jig
GB200 NVL4 NVLink interposer board removal fixture
GB200 NVL4 TIM Jig
T15 screwdriver
T10 bit together with torque wrench
GPU cold plate handle assembly
Thermal interface materials for MCIO configuration
Thermal interface materials for Dual CX8 mezzanine module configuration
For gap pad, putty pad, and PCM locations and instruction, see Gap pad, putty pad, and PCM identification and location.
Before replacing the gap pad, putty pad, or PCM, gently clean the surface with an alcohol cleaning pad.
Hold the gap pad, putty pad, or PCM carefully to avoid deformation. Make sure no screw hole or opening is blocked by the gap pad, putty pad, or PCM material.
Read Installation Guidelines and Safety inspection checklist to ensure that you work safely.
Turn off the corresponding DWC tray that you are going to perform the task on.
Disconnect all external cables from the enclosure.
Use extra force to disconnect QSFP cables if they are connected to the solution.
To avoid damaging the water loop, always use the water loop carrier when removing, installing or folding the water loop.
Go to Drivers and Software download website for ThinkSystem SC777 V4 to see the latest firmware and driver updates for your server.
Go to Update the firmware for more information on firmware updating tools.
Procedure
Install the CX8 mezzanine module or the MCIO breakout board. See Install a CX8 mezzanine module or Install the MCIO breakout board.
Install the E3.S drive cables. See Internal cable routing.
Install the PCIe riser cables. See Internal cable routing.
Follow the sequence below to connect the GB200-NVL4 board cables:
(Left-side GB200-NVL4 board only) Install the HMC module. See Install the HMC module.
Install the NVLink bridge. See Install the NVLink interposer board.
Install the rear wall. See Install the rear wall.
Complete cable routing for bus bar connector module sideband cable and System management sideband cable.
Install the cross bar. See Install the cross bar.
Install the tray cover. See Install the tray cover.
Install the tray into the enclosure. See Install a tray in the enclosure.
- Connect all required external cables to the solution.NoteUse extra force to connect QSFP cables to the solution.
Check the power LED on each node to make sure it changes from fast blink to slow blink to indicate all nodes are ready to be powered on.
Update the vital product data (VPD). See Update the Vital Product Data (VPD).
Machine type number and serial number can be found on the ID label, see Identify the solution and access the Lenovo XClarity Controller.