Performing a switchback
Starting with Storage Manager 9.6, you can perform a switchback operation that restores control to the original MetroCluster site (Site B) after the system has completed a successful switchover operation.
Before you begin
Before you perform a switchback operation, you must complete the following tasks:You must prepare the MetroCluster sites by Performing a negotiated switchover or Performing a unplanned switchover.
If errors occurred during the healing operation, you must follow the displayed instructions to fix them.
If the state of the remote site is displayed as
Getting ready for switchback
, then the aggregates are still resynchronizing. You should wait until the status of the remote site indicates that it is ready for switchback.