Powering off and powering on a data center
You must know how to power off and power on a data center for the purpose of site maintenance or to relocate a site to another location.
About this task
If a site needs to be relocated and reconfigured (if you need to expand from a four-node to an eight-node cluster, for example), these tasks cannot be completed at the same time. This procedure only covers the steps that are required to perform site maintenance or to relocate a site without changing its configuration.Note
This procedure is for use in both MetroCluster IP and FC configurations.