Power considerations
Power requirements and issues to consider when planning for your Lenovo ThinkAgile CP installation.
In planning for the power needs of the ThinkAgile CP solution, consider the following issues:
Ensure that the correct number of power receptacles is available based on the quantity of nodes.
Ensure that the power cords ordered match the power receptacles in the customer’s rack.
Ensure that power cords are ordered with lengths that allow them to connect to the customer-provided PDUs.
Device | Number of power supplies | PSU voltage | PSU max voltage | Heat generation (BTUs) |
---|---|---|---|---|
Network interconnect CP-I-10 | 2 | 100–240 VAC | 400 watts | |
Compute block CP-CB-10 | 2 | 220V | 2000 watts | Minimum configuration (with one minimal configuration node): 604.1 BTU per hour (177 watts) Maximum configuration (with four maximal configuration nodes): 7564.4 BTU per hour (2610 watts) |
Storage block CP-SB-10 | 2 | 220V | 2000 watts | Minimum configuration (with one minimal configuration node): 604.1 BTU per hour (177 watts) Maximum configuration (with four maximal configuration nodes): 7564.4 BTU per hour (2610 watts) |