Remove the power distribution board

Use this information to remove the power distribution board.

About this task

Required tools

Make sure you have the required tools listed below in hand to properly replace the component.

  • Water loop kits

    • SD650-I V3 Water loop service kit (03KH870)

    • Conduction plate parts (03KH864) (Only damaged parts needs to be replaced)

    • M.2 Putty pad kit (03LD666)

  • Drive gap pad or putty pad kits according to the drives installed in the tray. See their respective replacement procedures for more information.

  • ConnectX series adapter putty pad kits according to the ConnectX adapter installed in the tray. See their respective replacement procedures for more information.

  • Screws and screwdrivers

    Prepare the following screwdrivers to ensure you can install and remove corresponding screws properly.
    Screwdriver TypeScrew Type
    Torx T10 head screwdriverTorx T10 screw
    Torx T30 head screwdriverTorx T30 screw
    Phillips #1 head screwdriverPhillips #1 screw
    Phillips #2 head screwdriverPhillips #2 screw
Attention
  • Read Installation Guidelines and Safety inspection checklist to ensure that you work safely.

  • Turn off the corresponding DWC tray that you are going to perform the task on.

  • Disconnect all external cables from the enclosure.

  • Use extra force to disconnect QSFP cables if they are connected to the solution.

  • To avoid damaging the water loop, always use the water loop carrier when removing, installing or folding the water loop.

Prepare the following screwdrivers to ensure you can install and remove corresponding screws properly.
Screwdriver TypeScrew Type
Torx T10 head screwdriverTorx T10 screw
Torx T30 head screwdriverTorx T30 screw
Phillips #1 head screwdriverPhillips #1 screw
Phillips #2 head screwdriverPhillips #2 screw

Procedure

Note
Depending on the model, your solution might look slightly different from the illustration.

  1. Make preparations for this task.
    1. Remove the tray from the enclosure. See Remove a DWC tray from the enclosure.
    2. Remove the tray cover. See Remove the tray cover.
    3. Remove the cross braces. See Remove the cross braces.
    4. Remove the DIMM comb. See Remove a DIMM comb.
    5. Remove memory modules. See Remove a memory module.
    6. Remove the M.2 backplane assembly. See Remove the M.2 backplane assembly.
    7. Remove the drive cage. See Remove a drive cage assembly.
    8. Remove the PCIe riser assembly. Depending on your configuration, see Remove a PCIe riser assembly (ConnectX-6), PCIe riser assembly replacement (ConnectX-7 NDR 200), or Remove a PCIe riser assembly (ConnectX-7 NDR 400).
  2. Remove two Torx T10 screws (per node); then, remove the VR (voltage regulator) clamp plate out of the node.
    Figure 1. VR clamp plate removal
    VR clamp plate removal
  3. Remove water loop screws (9x Torx T10 screws per node) with a torque screwdriver set to the proper torque.
    Note
    For reference, the torque required for the screws to be fully tightened/removed is 5.0+/- 0.5 lbf-in, 0.55+/- 0.05 N-M.
    Figure 2. Water loop screw removal
    Water loop screw removal
  4. Remove the following screws to loosen the quick connect.
    • Two Torx T10 screws (per node) on the quick connect.

    • Five Torx T10 screws (per node) on the rear of the node.

    Figure 3. Quick connect screw removal
    Quick connect screw removal
  5. Orient the water loop carrier with the guide pin; then, gently put the water loop carrier down and ensure it is seated firmly on the water loop.
    Figure 4. Water loop carrier installation
    Water loop carrier installation
  6. Tighten water loop carrier screws (12x Phillips #2 screws per node).
    Figure 5. Water loop carrier screws installation
    Water loop carrier screws installation
  7. Loosen processors properly.
    1. Fully loosen all Torx T30 captive screws (8x Torx T30 captive screws per node) on cold plates with a general screwdriver until they stop, following the removal sequence shown on the cold plate label.

      Note
      For reference, the torque required for the screws to be fully tightened/removed is 10+/- 2.0 lbf-in, 1.1+/- 0.2 N-m.
      Attention
      To prevent damage to components, make sure that you follow the indicated loosening sequence.
    2. Rotate all anti-tilt wire bails (8x anti-tilt wire bails per node) inwards to the unlocked position.

    Figure 6. Loosening processors
    Loosening processors
  8. Carefully rotate the water loop so one half is sitting on top of the other half.
    Figure 7. Folding the water loop
    Folding the water loop
  9. Remove the power distribution board.
    1. Remove the five Phillips #1 screws (per node).
    2. Gently pull the power distribution board connector to disconnect it from the system board.
    3. Carefully pull the power distribution board inwards to disengage it from the node.
    Note

    Use a 3/16" hex head screwdriver to ensure the proper removal and installation.

    Figure 8. Power distribution board removal
    Power distribution board removal
After you finish