See this section to learn how to install the server to the rails.
Procedure
- For 2U, four node enclosure; reduce the weight by removing all the nodes, power supply units, fans, and SMM from the enclosure.
Figure 1. Removing components to reduce enclosure weight![Removing components to reduce enclosure weight](st650_v2-rail-004rail-350.png)
- Align and place the enclosure or chassis onto the rails; then, slide it into the rack along the rails.
Figure 2. Installing 2U, four node enclosure into rails![Installing 2U, four node enclosure into rails](st650_v2-rail-005a_rail-450.png)
Figure 3. Installing tower server into rails![Installing tower server into rails](st650_v2-rail-005b_rail-450.png)
![3-person lift required](3_person_lift-173.png)
For tower server installation, use safe practices when lifting.
- Secure the captive screws.
- Reinstall all the server components that you removed.