Use this information to install the manifold in an in-row direct water cooling system.
About this task
Important
This task must be operated by trained technicians that are certified by Lenovo Service. Do not attempt to remove or install the part without proper training and qualification.
Contact Lenovo Professional Services team for help when installing the part for the first time.
CAUTION
The coolant might cause irritation to the skin and eyes. Avoid direct contact with the coolant.
S002
CAUTION
The power-control button on the device and the power switch on the power supply do not turn off the electrical current supplied to the device. The device also might have more than one power cord. To remove all electrical current from the device, ensure that all power cords are disconnected from the power source.
S011
CAUTION
Sharp edges, corners, or joints nearby.
S038
CAUTION
Eye protection should be worn for this procedure.
S040
CAUTION
Protective gloves should be worn for this procedure.
S042
DANGER
危险
Risk of electric shock due to water or a water solution which is present in this product. Avoid working on or near energized equipment with wet hands or when spilled water is present.
Attention
Power off the node (see Power off the node); then, disconnect all external cables from the node.
Prevent exposure to static electricity, which might lead to system halt and loss of data, by keeping static-sensitive components in their static-protective packages until installation, and handling these devices with an electrostatic-discharge wrist strap or other grounding system.
Ensure proper handling procedures are followed when working with any chemically treated coolant used in the rack cooling system. Ensure that material safety data sheets (MSDS) and safety information are provided by the coolant chemical treatment supplier and that proper personal protective equipment (PPE) is available as recommended by the coolant chemical treatment supplier. Protective gloves and eyewear may be recommended as a precaution.
This task requires two or more people.
Procedure
Install the manifold.
Figure 1. Installing the manifold
Hold the manifold with both hands, and mount it onto the rack cabinet.
Align the spools with holes, and clutch the cabinet.
Remove the rubber quick connect plug covers from the ports on the manifold.
Connect the plug to the manifold port.
Install the hose kit to the manifold.
Figure 3. Installing the hose kit
1 17 mm wrench
Connect the hose kits to both manifolds.
Wrap the interface around with the clamp.
Close the clamp.
Lift the screw upright.
Tighten the screw and make sure that it is secured.
Install the bleeder kit to the manifold supply side.
Figure 4. Installing the bleeder kit to the supply side
Remove the rubber quick connect plug covers from the ports on the manifold.
Plug the bleeder kit to the manifold.
To push the air out of the manifold supply side, connect facility supply to manifold return.
Figure 5. Facility supply to manifold return
Press the button on the ball valve switch.
Rotate both switches open and stop at around 1/4 of 90 degrees.
Attention
Open the ball valves on 1 manifold return side and 2 facility supply side, while keep manifold supply side closed.
Do not fully open the ball valves, or the water flow gets too rapid to contain.
Slowly open the bleeder valve to conduct the air out of the hose. Close the bleeder valve once a steady stream of water flows into the bucket or there are only minimal bubbles in the bleeder hose.
Figure 6. Opening the bleeder valve on the supply side
Install the bleeder kit to the manifold return side.
Figure 7. Installing the bleeder kit on the return side
Remove the rubber quick connect plug covers from the ports on the manifold.
Plug the bleeder kit to the manifold.
To push the air out of the manifold return side, connect facility supply to manifold supply.
Figure 8. Facility supply to manifold supply
Press the button on the ball valve switch.
Rotate both switches open and stop at around 1/4 of 90 degrees.
Attention
Open the ball valves on 1 manifold supply side and 2 facility supply side, while keep manifold return side closed.
Do not fully open the ball valves, or the water flow gets too rapid to contain.
Slowly open the bleeder valve to conduct the air out of the hose. Close the bleeder valve once a steady stream of water flows into the bucket or there are only minimal bubbles in the bleeder hose.
Figure 9. Opening the bleeder valve on the return side
(For precaution) To make sure that the air inside is as little as possible, re-install the bleeder kit back to manifold supply side and do it one more time. Close the bleeder valve once a steady stream of water flows into the bucket or there are only minimal bubbles in the bleeder hose.
Figure 10. Opening the bleeder valve on the supply side
Once completed, connect the supply and return of manifold and facility correspondingly. Fully open all connections on both supply and return sides.
Figure 11. Opening ball valves
Note
1 Manifold supply connects to 2 facility supply
3 Manifold return connects to 4 facility return
Press the button on the ball valve switch.
Rotate the switch to fully open the valves as illustrated above.