Review the system reliability guidelines to ensure proper system cooling and reliability.

Make sure the following requirements are met:
  • A power supply or filler must be installed in each power-supply bay.
  • Adequate space around the server must be spared to allow server cooling system to work properly. Leave approximately 50 mm (2.0 in.) of open space around the front and rear of the server. Do not place any object in front of the fans.
  • For proper cooling and airflow, refit the front bezel before you connect power to the server. Do not operate the server with the front bezel removed.
  • Cabling instructions that come with optional components must be followed.
  • A failed fan must be replaced within 48 hours since malfunction.
  • A removed hot-swap fan must be replaced within 30 seconds after removal.
  • A removed hot-swap drive must be replaced within two minutes after removal.
  • A removed hot-swap power supply must be replaced within two minutes after removal.
  • Every air baffle that comes with the server must be installed when the server starts (some servers might come with more than one air baffle). Operating the server with a missing air baffle might damage the processor.
  • All processor sockets must contain either a socket cover or a processor with heat sink.
  • When more than one processor is installed, fan population rules for each server must be strictly followed.