Install the upper power distribution board
Use this information to install the upper power distribution board.
About this task
Attention
Read the Installation Guidelines to ensure that you work safely.
Procedure
Figure 1. Upper power distribution board installation
![Upper power distribution board installation](sd630v2_038-300.png)
![Upper power distribution board installation](sd630v2_038-300.png)
Note
Before installing the upper power distribution board, make sure that the lower power distribution board and enclosure air baffles have been installed into the enclosure (see Install the lower power distribution board and Install the enclosure air baffles).
- Install the upper power distribution board into the enclosure.
- Tighten the captive screws and connect the interconnect cables for power distribution boards.
After you finish
- Reinstall the components listed below into the enclosure in the following order:
Enclosure cover (see Install the enclosure cover).
Compute node(s) (see Install a compute node in the enclosure).
System Management Module 2 (see Install the hot-swap SMM2).
Power supplies (see Install a hot-swap power supply).
Install the solution back to the rack if necessary.
Reconnect power cords and all external cables.
Check the power LED on each node to make sure it changes from fast blink to slow blink to indicate the node is ready to be powered on.
Demo video