Install the front fan control board
Follow instructions in this section to install the front fan control board. The procedure must be executed by a trained technician.
About this task
Attention
- Read Installation Guidelines and Safety inspection checklist to ensure that you work safely.
- Touch the static-protective package that contains the component to any unpainted metal surface on the server; then, remove it from the package and place it on a static-protective surface.
- Install the 12V front fan control board when using 3200W power supplies, and the 54V front fan control board when using 3800W power supplies.
Note
Make sure you have a torque screwdriver available to properly replace the component.
Depending on the configuration, select the corresponding installation procedures:
12V front fan control board
Procedure
After you finish
- Reinstall the front fans. See Install a hot-swap fan.
- Push the system shuttle fully into the chassis.
Lift the two lock latches on both sides of the shuttle.
Slide the shuttle into the chassis.
Push the shuttle fully into the chassis.
Rotate the two release levers until they lock into place.
Figure 3. System shuttle installation

- Complete the parts replacement. See Complete the parts replacement.
54V front fan control board
Procedure
After you finish
- Reinstall the front fans. See Install a hot-swap fan.
- Push the system shuttle fully into the chassis.
Lift the two lock latches on both sides of the shuttle.
Slide the shuttle into the chassis.
Push the shuttle fully into the chassis.
Rotate the two release levers until they lock into place.
Figure 6. System shuttle installation

- Complete the parts replacement. See Complete the parts replacement.
Give documentation feedback