Use this information to install the carrier board.

About this task

Important
Gap pad/putty pad replacement guidelines
  • To identify the gap pad/putty pad location and orientation, see:

  • Before replacing the gap pad/putty pad, gently clean the interface plate or the hardware surface with an alcohol cleaning pad.

  • Hold the gap pad/putty pad carefully to avoid deformation. Make sure no screw hole or opening is blocked by the gap pad/putty pad material.

  • Do not use expired putty pad. Check the expiry date on putty pad package. If the putty pads are expired, acquire new ones to properly replace them.

Required tools

Make sure you have the required tools listed below in hand to properly replace the component.

  • SD665-N V3 Water Loop Service Kit (The water loop carrier in the Service Kit is reusable, it is recommended to keep it at the facility where the server operates for future replacement needs.)

  • SD665-N V3 Water Loop Putty Pad Kit

  • SD665-N V3 SXM5 PCM Fixture

  • SXM5 PCM Kit (for removing PCM from GPU)

    Putty pad cannot be reused. Whenever the water loop is removed, putty pads must be replaced with new ones before reinstalling the water loop.

  • Screws and screwdrivers

    Prepare the following screwdrivers to ensure you can install and remove corresponding screws properly.
    Screw TypeScrewdriver Type
    Torx T10 screwTorx T10 head screwdriver
    Torx T15 screwTorx T15 head screwdriver
    Phillips #1 screwPhillips #1 head screwdriver
    Phillips #2 screwPhillips #2 head screwdriver
Attention
  • Read Installation Guidelines and Safety inspection checklist to ensure that you work safely.

  • Turn off the corresponding DWC tray that you are going to perform the task on.

  • Disconnect all external cables from the enclosure.

  • Use extra force to disconnect QSFP cables if they are connected to the solution.

  • To avoid damaging the water loop, always use the water loop carrier when removing, installing or folding the water loop.

  • A torque screwdriver is available for request if you do not have one at hand.

Firmware and driver download: You might need to update the firmware or driver after replacing a component.

Procedure

  1. Rotate the GPU board retention clips and handle towards the GPU board.
    Figure 1. GPU board retention clips and handles rotation
    Rotate the GPU board retention clips and handles
  2. Install the carrier board.
    1. Hold the carrier board at an angle and align it with the guide pins on the tray; then, install the carrier board to the tray.
    2. Push the carrier board towards the GPU board to connect it to the GPU board.
    Figure 2. Carrier board installation
    Carrier board installation
  3. Secure the carrier board to the GPU board.
    1. Insert the GPU board retention clips into the slots on the carrier board.
    2. Rotate the GPU board handle toward the GPU board, and press it down to lock the carrier board in place.
    Figure 3. Securing the carrier board to the GPU board
    Securing the carrier board to the GPU board
  4. Install the two standoffs to the carrier board.
    Figure 4. Installing carrier board standoffs
    Installing carrier board standoffs
  5. Connect the carrier board power cable.
    Figure 5. Connecting carrier board power cable
    Connecting carrier board power cable
    CableFrom (carrier board)To (GPU node power distribution board)
    1 Carrier board power cablePower and side band connectorPower connector
After you finish
  1. Install the network board. See Install the network board.

  2. Install the MCIO cables. Follow the guidance and routing information in Internal cable routing.

  3. Install the bus bar. See Install the bus bar.

  4. Install the cross braces. See Install the cross braces.

  5. Install the tray cover. See Install the tray cover.

  6. Install the tray into the enclosure. See Install a DWC tray in the enclosure.

  7. Connect all required external cables to the solution.
    Note
    Use extra force to connect QSFP cables to the solution.
  8. Check the power LED on each node to make sure it changes from fast blink to slow blink to indicate all nodes are ready to be powered on.