Use this information to complete the installation.

To complete the installation, complete the following steps:

  1. If you removed the fan assembly, reinstall it (see Installing the fan assembly.
  2. If you removed the air baffle, reinstall it (see Replacing the air baffle).
  3. If you removed the left sidecover, replace it (see Replacing the left-side cover).
  4. Reconnect the cables and power cords (see Connecting the cables).
  5. Update the server configuration (see Updating the server configuration).
  6. Install the server in the rack cabinet (see the Tower to Rack Installation Instructions that is included in the separately ordered rack package) if necessary.
  7. Slide the server back into the rack, if necessary.
  8. Start the server. Confirm that is starts correctly and recognizes the newly installed devices, and make sure that no error LEDs are lit.
  9. Complete the additional steps in Instructions for Business Partners.