Use this information to remove the power distribution board.

About this task

Required tools

Make sure you have the required tools listed below in hand to properly replace the component.

  • SD665-N V3 Water Loop Service Kit (The water loop carrier in the Service Kit is reusable, it is recommended to keep it at the facility where the server operates for future replacement needs.)

  • SD665-N V3 Water Loop Putty Pad Kit

  • SD665-N V3 OSFP Putty Pad Kit

    Putty pad cannot be reused. Whenever the water loop is removed, putty pads must be replaced with new ones before reinstalling the water loop.

  • Drive gap pad or putty pad kits according to the drives installed in the tray. See their respective replacement procedures for more information.

  • Screws and screwdrivers

    Prepare the following screwdrivers to ensure you can install and remove corresponding screws properly.
    Screwdriver TypeScrew Type
    Hex screw (GPU node water loop)6 mm hex head screwdriver
    Hex screw (OSFP module conduction plate)4.5 mm hex head screwdriver
    Torx T10 head screwdriverTorx T10 screw
    Torx T20 head screwdriverTorx T20 screw
    Phillips #2 head screwdriverPhillips #2 screw
    3/16" hex head screwdriverM3 screw
Attention
  • Read Installation Guidelines and Safety inspection checklist to ensure that you work safely.

  • Turn off the corresponding DWC tray that you are going to perform the task on.

  • Disconnect all external cables from the enclosure.

  • Use extra force to disconnect QSFP cables if they are connected to the solution.

  • To avoid damaging the water loop, always use the water loop carrier when removing, installing or folding the water loop.

Procedure

Note
Depending on the model, your solution might look slightly different from the illustration.

  1. Make preparations for this task.
    1. Remove the tray from the enclosure. See Remove a DWC tray from the enclosure.
    2. Remove the tray cover. See Remove the tray cover.
    3. Remove the cross braces. See Remove the cross braces.
    4. Remove the DIMM comb. See Remove a DIMM comb.
    5. Remove memory modules. See Remove a memory module.
    6. Remove the M.2 backplane assembly. See Remove the M.2 backplane assembly.
      Note
      The M.2 backplane cold plate needs to be removed as well.
    7. Remove the bus bar. See Remove the bus bar.
    8. Remove the MCIO cables. Follow the guidance and routing information in Internal cable routing.
    9. Remove the drive cage. See Remove a drive cage assembly.
    10. Remove the OSFP module. See Remove the OSFP module.
  2. Remove the two Hex screws from the OSFP module with a 4.5 mm hex head screwdriver.
    Figure 1. OSFP module conduction plate Hex screws removal
    OSFP module conduction plate Hex screws removal
  3. Remove the OSFP module conduction plate. With alcohol cleaning pads, wipe of any remaining putty pads from the conduction plate.
    Screw TypeScrewdriver Type
    1 M3x5 screw (x3)Phillips #1 head screwdriver
    2 M3 screw (x2)T10 screwdriver
    Figure 2. OSFP module conduction plate removal
    Removing the OSFP module conduction plate
  4. Remove the five Torx T10 screws to loosen the quick connect.
    Note
    For reference, the torque required for the screws to be fully tightened/removed is 5.0+/- 0.5 lbf-in, 0.55+/- 0.05 N-M.
    Figure 3. Quick connect screw removal (Compute node)
    Quick connect screw removal
  5. Remove water loop screws and quick connect screws (14x Torx T10 screws per node) with a torque screwdriver set to the proper torque.
    Note
    • For reference, the torque required for the screws to be fully tightened/removed is 5.0+/- 0.5 lbf-in, 0.55+/- 0.05 N-M.

    • When removing the 1 VR cold plate screws (x2), remove the washers, too. Make sure to keep the washers for future use.

      Figure 4. VR cold plate screws with washer
      VR cold plate screws with washer
    Figure 5. Water loop screw removal

    1 VR cold plate screws (x2)


  6. Remove processor cold plate screws (12x Torx T20 screws per node). Follow the screw sequence specified on the processor cold plate label and loosen the screws with a general screwdriver. Fully loosen each screw; then, proceed to the next screw.
    Note
    For reference, the torque required for the screws to be fully tightened/removed is 1.12-1.46 newton-meters, 10-13 inch-pounds
    Figure 6. Processor cold plate label

    Fully loosen each screw in this order: 6 > 5 > 4 > 3 > 2 > 1


    Processor cold plate label
    Figure 7. Processor cold plate removal
    Processor cold plate removal
  7. Orient the water loop carrier with the guide pin; then, gently put the water loop carrier down and ensure it is seated firmly on the water loop.
    Figure 8. Water loop carrier installation (Compute node)
    Water loop carrier installation (Compute node)
  8. Tighten water loop carrier screws (x12 Phillips #2 screws).
    Note
    Select screw holes marked as R on the rear of the shipping bracket.
    Figure 9. Water loop carrier screws installation (Compute node)
    Water loop carrier screws installation (Compute node)
  9. Rotate the latch on the water loop carrier to separate the water loop from processors.
    Figure 10. Separate water loop from processor
    Separate water loop from processor
  10. Carefully rotate the water loop so one half is sitting on top of the other half.
    Figure 11. Folding the water loop
    Folding the water loop
  11. Remove the power distribution board.
    1. Remove the five M3 screws (per node) with a 3/16" hex head screwdriver.
    2. Gently pull the power distribution board connector to disconnect it from the system board.
    3. Carefully pull the power distribution board inwards to disengage it from the node.
    Note

    Use a 3/16" hex head screwdriver to ensure the proper removal and installation.

    Figure 12. Power distribution board removal
    Power distribution board removal
  12. With an alcohol cleaning pad, wipe off any remaining thermal grease, gap pads, and putty pads from the processor and water loop.
After you finish

If you are instructed to return the component or optional device, follow all packaging instructions, and use any packaging materials for shipping that are supplied to you.

Demo video

Watch the procedure on YouTube