Skip to main content

Install the cable holder frame and baffle assembly

Follow instructions in this section to install the cable holder frame and baffle assembly. The procedure must be executed by a trained technician.

About this task

Attention
  • Read Installation Guidelines and Safety inspection checklist to ensure that you work safely.
  • Touch the static-protective package that contains the component to any unpainted metal surface on the server; then, remove it from the package and place it on a static-protective surface.
  • Two people and one lifting device on site that can support up to 400 lb (181 kg) are required to perform this procedure. If you do not already have a lifting device available, Lenovo offers the Genie Lift GL-8 material lift that can be purchased at Data Center Solution Configurator. Make sure to include the Foot-release brake and the Load Platform when ordering the Genie Lift GL-8 material lift.

Procedure

Place the cable holder frame and baffle assembly above the GPU complex, and slide it forward into the system shuttle.
Figure 1. Cable holder frame and baffle assembly installation
Cable holder frame and baffle assembly installation

After you finish

  1. Connect the cables to the power distribution board. See below for more information.
  2. Reinstall the compute tray. See Install the compute tray.
  3. Connect the cables to the PSU interposer. See below for more information.
  4. Reinstall the system shuttle. See Install the system shuttle.
  5. Complete the parts replacement. See Complete the parts replacement.